Projects through the years

Projects through the years

Client
nacional
Industry
Electrical infrastructure and maintenance
Location
Cuyo, Argentina.
The Technical Challenge

Sustain technical continuity in electrical projects and long-term maintenance for generation, transformation, and auxiliary service assets.

The INELCO Solution

Throughout the years, INELCO participated in the assembly of transformer stations such as Nihuil IV in Valle Grande, Punta Rieles, Cuesta del Viento, and Jachal, consolidating field experience in critical infrastructure for power generation and transmission.

This journey was complemented by maintenance at TS Nihuil I, II, III, and IV, as well as the installation of auxiliary systems and driving force at Agua del Toro, the manufacturing of power and control systems, and the integration of emergency pumping systems as part of technical continuity sustained over time.

Special machinery assembly

Special machinery assembly

Client
nacional
Industry
Special machinery and electromechanical integration
Location
Cuyo, Argentina.
The Technical Challenge

Integrate electromechanical assembly, control, and commissioning in special machinery with lifting, palletizing, and bagging equipment of varying complexity.

The INELCO Solution

INELCO handled the manufacturing, supply, and electrical assembly of MCCs, PLCs, and VFDs for personnel lifting equipment, integrating switching, power, and control for TS Caris, Vulcano, Vespa, Marte, Venus, and Minerva systems.

The scope also included the electromechanical assembly of Natrotech palletizers, robotic palletizing arms, and their commissioning, along with maintenance tasks and operational adjustments to sustain service continuity and safety.

For the bagging lines, the electrical assembly of National Bulk Equipment bulk bag fillers was executed, including commissioning and calibration, as well as single and rotary baggers with Haver applicators to complete the full line integration.