The Technical Challenge

Integrate power, drives, control, and electromechanical assembly in hydration, micronizing, and grinding plants with high continuous process demand.

The INELCO Solution

INELCO executed the electrical assembly of the hydration plant and the manufacturing of LVDPs and power MCCs for the lime micronizing plant, including drives, command and control MCCs, and a 315 kW variable frequency drive for a ball mill as part of a turnkey project.

The scope also covered the electrical assembly of the coke grinding plant, including cabling, MCC manufacturing, cable laying, automation, SCADA integration, and commissioning to complete the process control and operation scheme.

Projects through the years

Projects through the years

Client
nacional
Industry
Electrical infrastructure and maintenance
Location
Cuyo, Argentina.
The Technical Challenge

Sustain technical continuity in electrical projects and long-term maintenance for generation, transformation, and auxiliary service assets.

The INELCO Solution

Throughout the years, INELCO participated in the assembly of transformer stations such as Nihuil IV in Valle Grande, Punta Rieles, Cuesta del Viento, and Jachal, consolidating field experience in critical infrastructure for power generation and transmission.

This journey was complemented by maintenance at TS Nihuil I, II, III, and IV, as well as the installation of auxiliary systems and driving force at Agua del Toro, the manufacturing of power and control systems, and the integration of emergency pumping systems as part of technical continuity sustained over time.